Development of a Risk-Based Maintenance Strategy for Facilities
Industry: Telecommunications
Location: Australia-wide
Type of contract: Consulting fee, reimbursements
Duration of contract: 3 weeks
Summary:
Transfield Worley Solutions developed a risk-based maintenance strategy
for a portfolio of nearly 9000 telecommunications facilities. The audit
identified the changes necessary to achieve desired improvements to the
maintenance function.
Transfield Worley Solutions was able to offer comprehensive
professional and technical advice on a consultancy basis, calling on broad
experience across several industries.
By applying best practice methodologies in risk evaluation and asset
management, Transfield Worley Solutions was able to deliver clear
recommendations for improvements to the client’s asset management
performance.
DEVELOPMENT OF A RISK-BASED MAINTENANCE STRATEGY FOR
FACILITIES
Scope & Approach:
Transfield Worley Solutions was engaged to help the client to quantify
and qualify the risks and rewards arising from the current maintenance
program for an asset portfolio consisting mostly of telecommunications
facilities.
The client wished to determine the need for increased or reduced
expenditure on maintenance and capital works. TWS developed data models
that classified the assets and allowed the grouping of asset integrity
data. Fourteen generic models were developed that identified and described
the significance of the entire portfolio of 9000 facilities under the
client’s care.
Monte Carlo simulation techniques were applied to assess degrees of
risk in the existing asset maintenance plan. A sensitivity analysis was
conducted to determine the impact of various expenditure scenarios on the
total cost of the asset maintenance program.
Outcomes & Benefits:
Transfield Worley Solutions was able to deliver a risk-based asset
degradation model that described the existing and predicted future
integrity of the facilities.
The model allowed the client to establish a systematic and methodical
approach to identifying the level of maintenance required to achieve the
minimum architectural condition standards. The model also allowed
life-cycle costs and consequent impacts on the bottom line to be
quantified in a manner the client could interpret easily.
The client had been juggling competing priorities for maintenance
expenditure, with a number of risks and a list of deferred works
developing under a contract mechanism of a decreasing budget and growing
asset portfolio. They utilised the degradation model to demonstrate that
the current levels of funding were insufficient for maintenance of
architectural condition and compliance with statutory requirements.
The benefits to the client included justified improvements to the
facilities architectural maintenance plans that are directly linked to
business needs. The revised plan:
- established an accurate deferred works list
- established agreed guidelines on the functional
life and condition standard required for buildings
- reduced unnecessary maintenance
- reduced high risk failures
- addressed probabilitites of failure
- improved the ability of the client to comply
with statutory requirements
- introduced measurable, auditable performance
standards and
- formed the basis for improved resource planning.
The client was able to realise a 26% saving on the existing scheduled
maintenance costs for the 27 most significant facilities, which
represented more than $800,000 per annum. Considerable savings in
maintenance costs were predicted for the remaining facilities.
The client was also able to demonstrate that funding increases for
deferred and capital works programs should be considered to improve the
architectural condition of a number of facilities.
|